Decision Gate 2 – Procurement of long lead items

 

 

execution_pil_blaaexecution_pil_blaaexecution_pil_blaaexecution_pil_blaaexecution_pil_blaaexecution_pil_blaaexecution_pil_blaaexecution_pil_blaa

 

  • A formal review undertaken prior to placement of key purchase orders like large electro motors, diesel engines, generators and major casting components
  • In order to pass this gate, the review must confirm that all pre-determined contractual, commercial, quality and technical requirements are fulfilled
  • Constructability analysis is carried out to ensure the design has reached the required quality and maturity to place orders for long lead items without jeopardizing quality, cost and schedule
  • Typically occurs 4-8 weeks after award of contract